Friday 28 October 2016

Filming plan

My partner and I decided to make a shooting schedule for each day of production. By doing this it enabled us to plan our time efficiently and kept us organised.

Day 1: Saturday 5th November 2016
Location 1 - Girls bedroom
Time
Description 
08:00 am 
Arrive at location
08:15 am
Set up filming equipment
08:25 am 
Test shots 
08:30 am 
Lyric rehearsal
09:00 am 
Overview of potential hazards
09:05 am
Begin filming 
10:30 am
Short break
10:45 am
Begin filming
12:00 am 
End of filming at location one
12:05 am
Pack up filming equipment 

Day 2: Sunday 6th November 2016
Location 2 - Marlow train station
Time
Description  
1:00 pm 
Arrive at location
1:05 pm
Set up filming equipment 
1:15pm
Overview of potential hazards
1:20 pm 
Film the train station platform 
1:30 pm 
Film the train approaching the platform 
1:33 pm
Move filming equipment
1:35 pm
Begin filming boy walking onto the train 
1:40 pm
Move filming equipment onto the train
1:45 pm
Film boy on the train 
1:55 pm
Move filming equipment
1:57 pm
Film boy stepping off the train
2:00 pm
Move filming equipment onto the platform
2:05 pm
Film the platform
2:10 pm
Pack up filming equipment

Day 3: Saturday 12th November 2016
Location - Marlow park/ river
Time
Description 
11:00 am 
Arrive at location
11:15 am
Set up filming equipment
11:25 am 
Test shots 
11:30 am 
Lyric rehearsal
12:00 am 
Overview of potential hazards
12:05 am
Begin filming 
01:30 pm
Short break
02:00 pm
Begin filming
03:00 pm 
End of filming at location one
03:05 pm
Pack up filming equipment 